Preliminary "stuff"
05/14/14 - Signed contract
05/17/14 - Met with NVR
05/28/14 - Guardian meeting
06/14/14 - Flooring selections
06/14/14 - Flooring selections
07/17/14 - Pre construction meeting
08/03/14 - Loan approval
08/03/14 - Loan approval
Construction Begin .......
Week 1 to Week 3 :
Day 1 (7/22/14) : Groundbreaking
Day 4 (7/25/14) : Footers
Day 7 (7/28/14) : Foundation Started
Day 13 (8/3/14) : Basement walls poured
Day 18 (8/8/14) : Forms Removed
Day 19 (8/9/14): Waterproofing
Week 4 :
Day 20(8/10/14): Plumbing
Day 21 (8/11/14): Drain Tile
Day 22 (8/12/14) : Back filled
Day 23 (8/13/14) : Slabs Prepped
Day 24 (8/14/14): Slabs Poured
Week 5 & 6:
Day 25 (8/15/14): Framing Started (Finally.....)
Day 29 (8/19/14): First floor framing done
Day 32 (8/22/14) : 2nd floor Framing started,most windows installed
Day 38 (8/28/14) : Roof and porch roof (no shingles); house wrapped
Day 40 (8/30/14) : HVAC & Roof Shingles
Day 32 (8/22/14) : 2nd floor Framing started,most windows installed
Day 38 (8/28/14) : Roof and porch roof (no shingles); house wrapped
Day 40 (8/30/14) : HVAC & Roof Shingles
Week 7:
Day 42 (9/1/14) : Framing Done
Day 42 (9/1/14) : Framing Done
Day 43 (9/2/14) : Plumbing, Guardian appointment
Day 44 (9/3/14) : Gas & electric
Day 45 (9/4/14) : Wiring by Guardian
Day 44 (9/3/14) : Gas & electric
Day 45 (9/4/14) : Wiring by Guardian
Day 46 (9/5/14) : Pre-drywall meeting
Day 47 (9/7/14) : Insulation installed
Week 8 & 9:
Day 48 (9/8/14) : Siding Started
Day 48 (9/8/14) : Siding Started
Day 51 (9/11/14): Drywall delivered & Siding Completed for 3 sides
Day 54 (9/14/14): Drywall hung
Day 57 (9/17/14): Siding and shutters complete
Week 10
Day 62 (9/22/14): Paint (1st coat)
Day 63 (9/23/14) Heat on & walls primed
Day 64 (9/24/14) : Trim, railings, cabinets, countertops & mirrors installed
Day 67 (9/27/14) : Recessed Lights, Bulbs,& Doors are done
Electricians installed Outlets too
Week 11
Day 69 (9/29/14) : Hardwood Flooring Started
Day 71 (10/1/14) : Flooring Completed & Ventilators, Dining Chandler InstalledDay 72 (10/2/14) : Tile Started in Bathroom , Vinyl Flooring in Laundry Room
Day 73 (10/3/14) : Trim work continues..
Day 74 (10/4/14) : Interior door knobs
Week 12
Day 76 (10/6/14) : Carpet on 2nd Floor, Guardian finishes
Day 77 (10/7/14) : Faucets are installed & Bathroom tile work finished
basement insulation, Toilet, exterior lighting
Day 78 (10/8/14) : Stove & microwave installed, Bath work completed, Doors installed
Electricians install lighting & driveway laid, gutters
Week 13
Day 83 (10/13/14) : Hardwood floors, touch up paint & drywall done
Day 84 (10/14/15) : Water lines connected, yard graded
Planned:
Day 85 (10/15/14) : Final walkthrough
Day 87 (10/17/14) : Closing
Day 87 (10/17/14) : Closing
No comments:
Post a Comment