Timeline

Preliminary "stuff"


05/14/14 - Signed contract
05/17/14 - Met with NVR
05/28/14 - Guardian meeting
06/14/14 - Flooring selections
07/17/14 - Pre construction meeting
08/03/14 - Loan approval

Construction Begin .......

Week 1 to Week 3 :
Day 1  (7/22/14) : Groundbreaking
Day 4  (7/25/14) : Footers
Day 7  (7/28/14) : Foundation Started
Day 13 (8/3/14)  : Basement walls poured
Day 18 (8/8/14)  : Forms Removed 
Day 19 (8/9/14): Waterproofing 

Week 4 :
Day 20(8/10/14): Plumbing
Day 21 (8/11/14): Drain Tile 
Day 22 (8/12/14) : Back filled
Day 23 (8/13/14) : Slabs Prepped
Day 24 (8/14/14):  Slabs Poured  

Week 5 & 6:
Day 25 (8/15/14): Framing Started  (Finally.....)
Day 29 (8/19/14): First floor framing done
Day 32 (8/22/14) : 2nd floor Framing started,most windows installed
Day 38 (8/28/14) : Roof and porch roof (no shingles); house wrapped
Day 40 (8/30/14) :  HVAC & Roof Shingles

Week 7:
Day 42 (9/1/14) : Framing Done 
Day 43 (9/2/14) : Plumbing, Guardian appointment
Day 44 (9/3/14) : Gas & electric

Day 45 (9/4/14) :  Wiring by Guardian
Day 46 (9/5/14) :  Pre-drywall meeting
Day 47 (9/7/14) : Insulation installed

Week 8 & 9:
Day 48 (9/8/14) : Siding Started
Day 51 (9/11/14):  Drywall delivered & Siding Completed for 3 sides
Day 54 (9/14/14):  Drywall hung
Day 57 (9/17/14):  Siding and shutters complete

Week 10
Day 62 (9/22/14):  Paint (1st coat)
Day 63 (9/23/14)   Heat on & walls primed
Day 64 (9/24/14) : Trim, railings, cabinets, countertops & mirrors installed
Day 67 (9/27/14) : Recessed Lights, Bulbs,& Doors are done
                              Electricians installed Outlets too

Week 11 
Day 69 (9/29/14) : Hardwood Flooring Started
Day 71 (10/1/14) : Flooring Completed & Ventilators, Dining Chandler Installed
Day 72 (10/2/14) : Tile Started in Bathroom , Vinyl Flooring in Laundry Room
Day 73 (10/3/14) : Trim work continues..
Day 74 (10/4/14) : Interior door knobs

Week 12 
Day 76 (10/6/14) : Carpet on 2nd Floor, Guardian finishes
Day 77 (10/7/14) : Faucets are installed & Bathroom tile work finished
                              basement insulation, Toilet, exterior lighting
Day 78 (10/8/14) : Stove & microwave installed, Bath work completed, Doors installed
                              Electricians install lighting & driveway laid, gutters  
                           
Week 13
Day 83 (10/13/14) : Hardwood floors, touch up paint & drywall done
Day 84 (10/14/15) : Water lines connected, yard graded   


Planned:
Day 85 (10/15/14) :  Final walkthrough
Day 87 (10/17/14) : Closing
                              